In simple terms
Part VII of the Act adopts, almost word for word, the regime the UNCITRAL Model Law introduced in 2006. It gives tribunals wide powers to protect the parties' position before the final award, and makes those measures enforceable through the courts.
What an interim measure is
Unless the parties agree otherwise, the tribunal may, at a party's request, grant interim measures (section 31(1)). An interim measure is any temporary measure, whether in the form of an award or another form, ordered before the final award (section 31(2)). It may require a party to:
- (a) make a provisional payment of money or dispose of property between the parties;
- (b) make an interim payment on account of costs, or provide security for costs;
- (c) maintain or restore the status quo pending the decision;
- (d) take action to prevent, or refrain from action likely to cause, current or imminent harm or prejudice to the process;
- (e) provide a means of preserving assets from which an award may be satisfied; or
- (f) preserve evidence that may be relevant and material.
Article 26 of the First Schedule repeats these powers for arbitrations under the Rules.
The conditions
For measures (a) to (e), the requesting party must satisfy the tribunal that (section 32(1)):
- harm not adequately reparable by damages is likely if the measure is not ordered, and that harm substantially outweighs the harm the measure is likely to cause the other party; and
- there is a reasonable possibility that it will succeed on the merits. This finding does not bind the tribunal when it later decides the merits.
For a measure to preserve evidence, these requirements apply only so far as the tribunal thinks appropriate (section 32(2)).
Preliminary orders without notice
Sometimes warning the other party would defeat the purpose of the measure, for example where it might move assets as soon as it hears of the application. A party may therefore apply, without notice, for an interim measure together with a preliminary order directing the other party not to frustrate the measure (section 33(1)). The tribunal may grant it if it considers that disclosure of the request risks frustrating the measure (section 33(2)), applying the same conditions as for interim measures (section 33(3)).
Strict safeguards apply (section 34):
- immediately after deciding the application, the tribunal must tell all parties about the request, the order and all communications about it;
- the other party must be given a chance to present its case at the earliest practicable time, and the tribunal must decide promptly on any objection;
- a preliminary order expires after 20 days, though the tribunal may then issue an interim measure adopting or modifying it after hearing the other party; and
- a preliminary order binds the parties but cannot be enforced by a court.
The must disclose to the tribunal all circumstances likely to be relevant to whether the order should be made or kept, and this duty continues until the other party has been heard (section 37(2)).
Modification, security, disclosure and liability
The tribunal may modify, suspend or terminate an interim measure or preliminary order on a party's application or, in exceptional circumstances, on its own initiative after notice (section 35). It may require the applicant to give security (section 36), and it must require security for a preliminary order unless that would be inappropriate or unnecessary. It may require a party to disclose promptly any material change in the circumstances (section 37(1)).
A party that obtains an interim measure or preliminary order is liable for the costs and damages it causes if the tribunal later decides that it should not have been granted, and the tribunal may award them at any stage (section 38). This is the arbitral equivalent of a cross-undertaking in damages.
Recognition and enforcement by the court
An interim measure issued by a tribunal is binding and, unless the tribunal says otherwise, will be enforced on application to the court, wherever it was issued (section 39(1)). The applicant must tell the court promptly if the measure is terminated, suspended or changed (section 39(2)), and the court may require security if the tribunal has not dealt with it (section 39(3)). Under paragraph 5 of the Third Schedule the application is made by originating notice of motion, with an exhibiting the arbitration agreement and the decision, identifying the parties, and stating how far the measure has not been complied with.
The court may refuse recognition or enforcement only (section 40):
- at the request of the party against whom it is invoked, on the grounds in section 63(2)(a)(i) to (iv) (incapacity, invalid agreement, lack of notice or inability to present its case, or matters beyond the submission), or because the tribunal's order on security was not complied with, or because the measure has been terminated or suspended; or
- on its own motion, if the measure is incompatible with the court's powers (though the court may reformulate it to fit its own procedures without changing its substance), or if the subject matter is not arbitrable or enforcement would be contrary to public policy.
The court's decision on these grounds has effect only for the enforcement application, and the court may not review the substance of the measure.
Interim measures from the court
The court has the same power to grant interim measures in relation to arbitration as in its own proceedings, exercised in a way that takes account of the features of international arbitration (section 41). Findings of fact the tribunal has already made on a relevant matter are conclusive. Under the Third Schedule, applications for preservative or interim relief must be determined within 30 days of filing.
The court's role is supportive. It should not grant relief that takes over decisions the parties gave to the tribunal: Channel Tunnel Group v Balfour Beatty (1993). Parties go to court rather than the tribunal mainly where the order must bind third parties, such as a bank holding the respondent's funds, where the tribunal has not yet been formed and there is no emergency arbitrator, or where coercive enforcement is needed at once.
In the Sierra Leone courts
In Timis Mining Corporation v Cape Lambert Resources [2021] SLCA 11 the Court of Appeal accepted that the court may grant interim measures in support of an arbitration, but held that the applicant must intend to arbitrate. A claimant that denied the arbitration clause applied could not rely on the court's supporting power, and its proper forum for interim relief in a London-seated arbitration was the English court.
Words and Latin in this note
- Frustration
- A contract ends, without either side being at fault, because performance has become impossible, illegal, or radically different from what was promised. A mere rise in cost is not enough. Open the note.
Memory map
Interim measures and preliminary orders
Key points
- Section 31
- Section 32
- Preliminary orders without notice last 20 days,…
More points
- The applicant pays costs and damages if the…
- Courts enforce interim measures on limited…
- Courts have their own interim powers under…
Cases
- Channel Tunnel Group Ltd v…
- Coppée-Lavalin SA/NV v Ken-Ren…
- Timis Mining Corporation SL Ltd v…
Key terms
- Affidavit
- Arbitration
Take-home points
- Section 31: the tribunal may order provisional payment, security, the status quo, anti- orders, preservation of assets and of evidence.
- Section 32: the applicant must show irreparable harm, a favourable balance of harm and a reasonable possibility of success.
- Preliminary orders without notice last 20 days, must be disclosed at once and cannot be enforced by a court (sections 33-34).
- The applicant pays costs and damages if the measure should not have been granted (section 38).
- Courts enforce interim measures on limited grounds without reviewing their substance (sections 39-40).
- Courts have their own interim powers under section 41; Third Schedule applications must be decided within 30 days.
Cases in this topic
- Channel Tunnel Group Ltd v Balfour Beatty Construction Ltd
- Coppée-Lavalin SA/NV v Ken-Ren Chemicals and Fertilizers Ltd
- Timis Mining Corporation SL Ltd v Cape Lambert Resources Ltd & Others
Related case law
Full judgments on Lanbuk on the same areas of law.
Lecture notes on this subject
- Arbitration Study Note 2: Dispute Resolution and the Arbitration AgreementArbitration
- Arbitration Study Note 1: ADR Compared with Court LitigationArbitration
- The Doctrine of Separability in ArbitrationArbitration
Other law notes by subject
Business and human rights
Civil procedure
- The Slip Rule and Judicial Finality: Correcting Errors in Court Orders in the UK and Sierra Leone
- Sierra Leone's Court System and Starting Civil Proceedings in the High Court
- Who Addresses the Court First in Closing Speeches, and Why
- Disposal of Cases on Points of Law under Order 17
- Garnishee Proceedings under Order 50
- Interlocutory and Final Judgments
Constitutional and administrative law
Contract law
Criminal procedure
- No Case Submission: Interpreting 'Otherwise Deals in or With' under the National Drugs Control Act 2008
- Legal Authorities for a No Case Submission on Drug Importation Charges
- No Case to Answer: Analysis of a Drug Importation Prosecution
- Criminal Procedure: Law School Notes
- Submission of No Case to Answer: Dealing in Prohibited Drugs
Environmental and climate law
Equity and trusts
Exam preparation
Family law
Human rights
International law
Radiation and nuclear safety law