Channel Tunnel Group Ltd v Balfour Beatty Construction Ltd
1993 · [1993] AC 334
Posted By lanbuk.com
- Facts
- The contractors building the Channel Tunnel had a contract with a two-stage dispute clause: disputes went first to a panel of experts and then to ICC in Brussels. A dispute arose about payment for the tunnel's cooling system, and the contractors threatened to stop work. Channel Tunnel Group sued in the English court for an to stop them.
- Issue
- Should the English court stay the action in favour of the agreed process, and should it grant an in support of an arbitration seated abroad?
- Held
- The action was stayed and no injunction was granted. The House of Lords held that the court had power to stay proceedings brought in breach of an agreement to use a two-stage process, even though the first stage was not itself arbitration. It had power to grant an interim injunction, but should not do so here, because the injunction would give Channel Tunnel Group the very relief it would seek from the panel and the arbitrators.
- Principle
- Parties who agree a staged dispute process will be held to it. A court supporting arbitration should not grant interim relief that pre-empts the decision the parties gave to the tribunal.
- Why it matters
- Supports the stay under section 9 of the 2022 Act and illustrates the limits of the court's supporting power to grant interim measures under section 41.