10. Commencing the arbitration

The notice of arbitration, the response, service, time limits and pre-conditions

Posted By lanbuk.com

In simple terms

An starts with a notice. The date it starts matters for limitation, and the notice must be served properly. Part V of the Act sets out what the notice must contain, how the replies and how time is counted.

Why the start date matters

The date on which an arbitration starts stops time running for limitation purposes. Section 3 applies the Limitation Act 1961 to domestic arbitral proceedings, so a claimant who starts too late may find the claim barred. A contract may also set its own shorter time limit for starting arbitration.

The notice of arbitration

Under section 23 a party wishing to arbitrate must send a Notice of Arbitration to the other party. Unless the parties agree otherwise, the arbitration starts on the date the respondent receives the notice (section 23(2)).

The notice must include (section 23(3)):

  • a demand that the dispute be referred to arbitration;
  • the names and contact details of the parties;
  • the arbitration agreement relied on;
  • the relevant contract clauses, or a brief description of the relationship;
  • a brief description of the claim and the amount involved;
  • the relief sought; and
  • a proposal on the number of arbitrators, the language and the place, if not already agreed.

It may also propose an arbitrator or appointing authority, or notify the claimant's own appointment of an arbitrator.

The response

Within 30 days of receiving the notice, the respondent must send a response (section 24). It must answer the notice and describe any counterclaim or set-off. It may also object that the tribunal lacks , propose a sole arbitrator, notify the respondent's own appointment, or start a separate claim against another party to the agreement. Any argument about whether the response is sufficient is for the tribunal (section 24(3)).

Serving notices and counting time

Section 25 allows a notice to be sent by any means that keeps a record of transmission, including email or fax to an address designated by the party. Without a designated address, a notice is received when physically delivered, or when delivered to the addressee's place of business, habitual residence or mailing address. If none of these can be found after reasonable efforts, a notice sent by registered letter or similar to the last-known address is treated as received. Section 91 has general rules on reckoning time and section 90 on service.

Pre-conditions to arbitration

Many contracts set out steps before arbitration can begin: negotiation between senior managers, mediation, or referral to an engineer or dispute board. These are called multi-tier or escalation clauses.

Whether such a step is binding depends on how certain it is. A clause requiring "friendly discussions" for a fixed period was enforced in Emirates Trading v Prime Mineral Exports (2014). A vague promise to try to mediate may be too uncertain to enforce. Where the step is binding, a court may stay litigation until it has been taken, as the House of Lords did in Channel Tunnel Group v Balfour Beatty (1993).

Extending contractual time limits

Section 26 deals with a clause that bars a claim unless the claimant starts arbitration, or some preliminary procedure, within a fixed time. The Centre or appointing authority may extend the time, and the court may do so only if the circumstances were outside what the parties reasonably contemplated and it would be just to extend, or if the other party's conduct makes it unjust to hold the claimant to the strict terms.

Emergency arbitration

If a party needs urgent relief before the tribunal is formed, it may apply for an emergency arbitrator under sections 28 to 30, or ask a court for interim protection under section 11. Both are covered in the chapter on emergency arbitration.

Memory map

Commencing the arbitration

Key points

  • Unless agreed otherwise, the arbitration starts…
  • The notice must identify the parties, the…
  • The respondent has 30 days to respond and may…

More points

  • Notices may be sent by any means that records…
  • The Limitation Act 1961 applies to domestic…
  • Binding pre-arbitration steps must be followed

Cases

  • Hayter v Nelson and Home…
  • Ellerine Bros (Pty) Ltd v Klinger
  • Emirates Trading Agency LLC v…
  • Channel Tunnel Group Ltd v…

Key terms

  • Arbitration

Take-home points

  • Unless agreed otherwise, the arbitration starts when the respondent receives the Notice of Arbitration (section 23(2)).
  • The notice must identify the parties, the agreement, the claim, the relief and proposals on arbitrators, language and place (section 23(3)).
  • The respondent has 30 days to respond and may raise jurisdiction and counterclaims (section 24).
  • Notices may be sent by any means that records transmission, including email to a designated address (section 25).
  • The Limitation Act 1961 applies to domestic arbitrations (section 3); contractual time bars may be extended under section 26.
  • Binding pre-arbitration steps must be followed; the court can stay litigation until they are.

Cases in this topic

Related case law

Full judgments on Lanbuk on the same areas of law.

Other law notes by subject

For study only. By lanbuk.com. Always check current sources and consult a qualified professional.

Cite this page

'Commencing the arbitration, Lanbuk on Arbitration' (Lanbuk) <https://www.lanbuk.com/llb/arbitration/commencement> accessed 24 November 2026

The accessed date is today's date. Check your course or publisher's style guide.

Community discussion

Community discussion is for learning only and is not legal advice. Never share client or confidential information. See the community guidelines.