Skip to content
Civil appeal

Tom Nyama v Salini Construttori Spa (CIV APP 36 of 2007) [2011] SLCA 34 (15 July 2011)

Posted By lanbuk.com

Tom Nyama v Salini Construttori Spa is a civil appeal from Sierra Leone on 15 July 2011. Cite it as [2011] SLCA 34. Search it by the party names, the citation [2011] SLCA 34, or Sierra Leone civil appeal.

Sierra Leone — Court of AppealPDF · 2.7 MB[2011] SLCA 34Civil appeal

Decided by:Justice Hamilton,Justice Salimatu Koroma,Justice Stronge,Justice Massally

To download the full judgment, go to the end of this page

What follows is the text read from the court's own file. The complete judgment is a PDF (2.7 MB), and the download button is at the foot of this page.

July 15, 2011

IN THE COURT OF APPEAL

Tom Nyama

Appellant

v.

Salini Construttori Spa

Respondent

CIV APP 36 of 2007

[2011] SLCA 34

Case brief

Court
Sierra Leone — Court of Appeal
Date
15 July 2011
Citation
[2011] SLCA 34
File number
CIV APP 36 of 2007
Proceeding
Civil appeal. Sierra Leone.

No headnote or brief is recorded for this judgment yet, so none is shown. Read the judgment below for the facts, the issues and what the court decided.

Only what is recorded for this judgment is shown. · Browse cases by topic

Pe IN TH ”

BETWEEN:

TOM NYAMA -

(doing business as TEKO AGRICULTURAL PROJECT)

AND

SALINI CONSTRUTTORI SPA -

(SALCOST)

Coram

Hon. Ms. Justice S. Koroma J.S.C.

Hon. Mr. Justice P.O. Hamilton J.S.C. Hon. Mr. Justice A. N. B. Stronge J.A.

SOLICITORS: A. S. Sesay Esq for Appellant

N. D. Tejan-Cole Esq for Respondent i a eas | 3 Cy 2011.

Judgment Delivered on the Day of

KOROMA J.S.C.

KOROMA J.S.C. - This is an Appeal against the J udgment of the Honourable Mr. Justice

J. E. Massaly J. deceased delivered by the Honourable Mrs. C. L. Taylor on the

9" of June 2006.

Background

The facts of the case according to the evidence is that in may of 1992 Salini Construttori

SPA (SALCOST) 4 foreign company doing business hereinafter called the Respondent) entered into an agreement llant

in Sierra Leone the

Respondent/ ( oing business as Teko Agricultural Project) the /Appe

with Tom Nyama (d t area of the

(hereinafter called the Appellant) to undertake the clearing of the catchmen dam and reserveir at Bumbuna which is being constructed by the Respondent. The paries signed the agreement in May 1992 and the contract period was from

1* May 1992 to 30" April 1994. The terms and conditions of the contract were detailed

8t

in the Letter of Intent signed by both parties. It was indicated the letter of intent would

serve as the contract until a formal contract was drawn up.

On the 21" August 1993 the Respondent drafted a letter headed “Bumbuna falls Hydro

Electric Project — Object: - Reservoir clearing project — claims, settlement and works suspension”. The gist of the letter was for a temporary suspension of the contract and it was also indicated that the Respondent could not fix a date for resumption of the

works. Each party’s obligations in the contract were set out in detail. Both parties signed

the agreement.

On the 23" June 1995 the Respondent again wrote to the Appellant suggesting that the

contract be terminated because since the suspension in 1993 no date could be envisaged

for resuming the works and with the added difficulties of the war it was pointless to continue with an indefinite suspension of the works.

The Appellant was opposed to the termination of the contract and proposed continuation tract. Subsequently, by letter dated 21 August The contract had lasted 15 (fifteen)

of the indefinite suspension of the con!

1995 the Respondent terminated the contract.

months. The Appellant issued a dated 24™ April 1996 against the Respondent for

Damages for breach of contract and consequential loss upon such breach of contract and

for costs.

gh Court action came before the Honourable J. E. Massaly J. now (Deceased) and s against

The Hi he, after reviewing the evidence gave Judgment in favour of the Respondent. Iti

that Judgment that the Appellant has appealed to this Court on three (3) grounds.

The Grounds of Appeal are as follows:

1. That the Learned Trial Judge’s conclusio onduct on the part of the Defendant, and

n that documents Tendered in Exhibits 2

‘L’ and ‘M’ were not a unilateral c

therefore dismissed the matter is erroneous - in that the suspension was not an

issue, but the termination of the contract.

2. That the Learned Trial Judge erred in that he did not address the question of

termination of the contract which is the thrust of the Appellant's case

3. That the Judgment is against the weight of the evidence.

| with the issue of the contract started with a letter from the ressed to the Appellant. This

Before considering the grounds of Appeal I will briefly dea’ between the parties. The transaction between the parties Respondent by its Site Manager on a day in May 1992 add: was headed “Letter of Intent”, ‘b’ of the preamble of the Letter of Intent stated “This

Letter of Intent is being issued as a temporary substitute pending signing of a formal

contract to enable work on the Reservoir area clearance to commence immediately”.

The letter contained all the terms and conditions of the parties pertaining to the clearance

of the dam/reservoir area. Most importantly the duration of the project was spelt out to commence on the 1 of May 1992 and end on the 30" April 1994 — in effect a period of e Letter of Intent and for all intents and purposes the

two years. Both parties signed th As far as the records go no

parties regarded this as the contract document of the project.

“formal contract” was thereafter signed. Neither party has disputed the validity of the

document signed.

Ground 1 (One)

The Appellant’s conte! e suspension of the contract was dealt with in Exhibit ‘H’ in letter

ondent dated 21°* August 1993 which both parties subsequently

ntion is that the suspension of the contract was the unilateral act of

the Respondent. Thi drafted by the Resp signed.

For clarity’s sake, I will reproduce two short portions of that document headed “Object: project — claims settlement and works suspension”.

we inform (sic) that you, that due to various reasons we

Reservoir clearing “Concerning the above project,

are forced to suspend the works. We assume that the activities will be resumed at a later stage, present moment. Therefore we wish to make the following proposal for a

but we are not able to fix

a date at the suspension of the works and of the subject agreement”.

temporary

The letter went on to detail the obligations of both the parties, and it ended with the following two paragraphs: The Contractor will sign a copy of this letter for acceptance of all the above clauses

and receipt of outstanding balance due him.

The Sub-Contractor Teko Agricultural Project declare also that by signing the subject letter has nothing else to claim from SALCOST Sierra Leone for the whole contractual period and during the suspension of the works, in connection with the agreement signed May 1992”,

It is clear from the two quoted segments of Exhibit ‘H’ that the suspension of the contract was proposed by the Respondent, but Exhibit ‘H’ clearly showed that it was however a negotiated agreement reached by both parties and this was further confirmed by Exhibit ‘M’ in which the Appellant dealing with other issues thereafter stated “J further stressed that I was comfortable with an indefinite suspension for as long as SALCOST

considered it unsafe for us to resume the clearing operations”.

In the light of this I find the Learned Trial Judge was correct in his conclusions that the suspension of the works and contract was not a unilateral act of the Respondent. I find no

merit in ground one (1) of the Appeal.

Ground 2 (Two)

This is a ground worthy of more . The Learned Trial Judge found that both the suspension and termination of the contract were not a unilateral conduct of the Respondent. I beg to differ. The issue of the termination of the contract is of a different

nature from the suspension of the contract which was endorsed by the Appellant.

The Respondent addressed a letter Exhibit ‘J’ to the Appellant on the 23" June 1995 which stated: “As the works are suspended since 1993 and no date can be envisaged for resuming the project, thus also considering the added difficulties created by the war

situation in the country we formally suggest to mutually convene a termination to our

agreement. You will agree that it is now pointless to continue with an indefinite

suspension of the works”.

I can understand why the Learned Trial Judge concluded that the termination was not unilateral. This I believe is due to the fact that Exhibit ‘J’ was couched as a proposal from the Respondent. However I disagree with his conclusion. It was almost 23 months after the suspension of the contract by both parties. However, it appears for reasons advanced by the Respondent including the war in Sierra Leone that it was a firm position they had reached, as the letter went on to state: “On the other hand should the project ever be resumed in the future, we shall be pleased to_consider_a new and_ up-to-date proposition from your side”.

Emphasis mine.

The Appellant in reply by Exhibit ‘K’ dated 29" June 1995 stated: “On the issue of convening a termination to our contract on the grounds of the current state of the security in the country, we consider your proposal not in our interest and therefore cannot accept such an arrangement. An extension to the indefinite suspension currently in force will probably be viewed as appropriate

in the light of the prevailing circumstances”.

Here lies the difference between the parties on this issue.

I find Exhibit ‘L’ dated 3 July 1995 much more illuminating in trying to second guess the Learned Trial Judge’s reason for reaching his conclusion that the termination was not unilateral. The Respondent stated in Exhibit ‘L’

«....we have agreed in view of the continued suspension of the works and the problems posed by security situation in the country to terminate our contract and the reciprocal obligations by mutual consent amicably and without further demands on each other”. This purported agreement was vehemently denied by the Appellant in

Exhibit ‘M’. I therefore conclude that this was a unilateral termination of the contract by

the Respondent albeit for alleged good reasons.

The Respondent in his amended Defence and Counter Claim, pleaded in paragraph 9 of the amended Defence that the head contract with the Government of Sierra Leone had been suspended. This led to the suspension of the contract between the parties as evidenced by a written agreement signed by both parties dated 21° August 1993.

AI

What we have is a situation in which the Respondent on evidence adduced had to suspend the works at the dam and reservoir with no idea when activities would be resumed. On the other hand the Appellant with full knowledge of the security situation

caused by the war was prepared to maintain the suspension of the contract for however

long that security situation lasted.

Many contracts expressly provide for performance to be excused if rendered impossible

to be concluded by unavoidable cause such as force majeure or . However in

this particular contract there was no such clause and indeed the Respondent did not raise

that as a defence.

y view that what is more relevant in a case of this nature which is silent as to the

bligations

It is m position of the parties in the event continued performance of the parties’ o'

becoming literally impossible is the “Doctrine of subsequent impossibility or ”

Applying the facts of the case to this doctrine, there is evidence from the Respondent that

the head contract had been suspended due to the security situation. This was not rebutted

by the Appellant. This evidence was further strengthened by the fact that expatriate

employees of the head contractor, the Respondent had left the country. Even the Site

Manager was not in the country to give evidence at the trial.

I hold that termination of the contract by the Respondent in this respect did not need the agreement of the Appellant. As far back as August 21", 1993 when the Appellant signed the agreement for the suspension of the contract he had acknowledged the impossibility of continuing with the performance of the contract. A valid contract can be brought to an

from the moment of impossibility (see paragraph 442 of Halbury’s laws of “Impossibility And F rustration in general”.

eleasing both parties from further

end generally England, 4" Edition under the rubric In a case of this nature the contract is discharged, r

performance.

The impossibility of continuing the contract was mentioned in Exhibit ‘L’ dated

3" July 1995 addressed to the Appellant by the Respondent where the manager clearly stated:

qr

“sees regretting the general situation forcing on both parties the impossibility of continuing the ‘works’.....”. I can safely conclude one of the consequences of this is that the event of war did not only affect the sub-contract but also the head contract. It is part of the evidence that all activities stopped and the site cleared after 21" August 1993

It is commonly held that the legal result of impossibility to perform such a contract lay

where they fall. So that money already paid is irrecoverable and money due under the contract for work already done is enforceable. So that a party who had performed only part of an entire contract could recover nothing. In this case under the agreement dated 21 August 1993, Exhibit ‘H’ the obligations of both parties were set out and the nt paid the amount that was agreed to be outstanding and the Appellant did

Responde declare that by signing che letter he had nothing to claim from the Respondent for the whole contractual period and during the period of suspension.

further buttressed by the

This issue of impossibility of performance of a contract can be

judgment of Lord Denning MR in the “Harbutts Plastacine Ltd V Wayne Tank and

Pump Co Ltd [1970] 1 All ER 225 in which he stated at page 233 “It is clear therefore that if the innocent party with full knowledge refuses to 1 the effect is that the status quo ante is preserved

accept the termination of the contrac Therefore each party has no right to sue for

and remains in force for both sides. damages for past or future breaches”.

I note that the counter claim by the Respondent was dismissed due to the failure of an

important witness to come to Sierra Leone to testify on issues raised. with the Jast points in this Appeal together. Apart from the impossibility years and there was

I will now deal

of performing the contract, the duration of the contract was two

nothing in the subsequent agreement which extended the duration of the contract. By

spondent, the contract spelt out

August 1995 when the contract was terminated by the Re April 1994 to be precise.

in Exhibit ‘H’ should have long come to an end, on the 30" I do agree with the Appellant that the Learned Trial Judge did not deal with the

termination exclusive of the suspension of the contract.

q3

However for reasons I have addressed this ground of Appeal has no merit and it therefore

fails. Having dealt with the legal position of the Doctrine of impossibility

performance of contracts which I believe is applicable to the essence of the appeal, I will ly and only as an intellectual!

or frustration of

deal with issues under paragraph 4 of the Appeal very briefl

exercise. Paragraph 13 (1-16) of the particulars of claim headed “ al position is that must be

particulars of loss”

itemised a long list of claims. However the leg pleaded with detailed particulars but more importantly strictly proved by evidence at the trial, this was so held in Macauley V Coker 1968 — 69 ALR SL

399. This in my view was not done by the Appellant. Furthermore, I hold that all those alleged losses occur

either or emanate from activities before 21 August 1993 when both parties signed

Exhibit ‘H’ and the Appellant declared that by signing the agreement and upon receipt of

payment made by the Respondent he could have no further claim against the Respondent

for the whole of the contractual period and during the suspension of the works. The

claim for special damages therefore fails.

In conclusion, I hold that there is no merit in any of the grouncs of Appeal and the

Appeal is hereby dismissed. I therefore order that costs of this Appeal shall be paid by

the Appellant to the Respondent. Such costs are to be taxed.

CF Mel

Hon. Ms. Justice S. Koroma J.S.C.

Hon. Mr. Justice P. O Hamilton J.S.C.

Citations and appeal history

Read from the judgments on Lanbuk: a link is shown only where a judgment's text carries the other's exact citation. The quotes are the court's own words, so you can see how the case was used.

No other judgment on Lanbuk is recorded as citing this one, and it cites none of them by citation. It may still be cited in judgments and reports that are not on Lanbuk.

Judges

The judges named in this report. Each page lists their other judgments on Lanbuk.

Counsel

The lawyers who appeared, as named in the judgment.

  • N.D. Tejan-Colefor the Respondent

How do I cite Tom Nyama v Salini Construttori Spa?

Cite Tom Nyama v Salini Construttori Spa as Tom Nyama v Salini Construttori Spa [2011] SLCA 34, which is its recorded neutral or law-report citation. The decision is from Sierra Leone — Court of Appeal on 15 July 2011. Use the citation box on this page to copy the reference.

Cite this page

Tom Nyama v Salini Construttori Spa [2011] SLCA 34 (Lanbuk, 9 October 2026) <https://www.lanbuk.com/cases/tom-nyama-v-salini-construttori-spa-civ-app-36-of-2007-2011-slca-ada5w> accessed 29 November 2026

The accessed date is today's date. Check your course or publisher's style guide.

Community discussion

Community discussion is for learning only and is not legal advice. Never share client or confidential information. See the community guidelines.