Habaş Sinai ve Tibbi Gazlar Isthisal Endüstri A.Ş. v Sometal S.A.L. [2010] EWHC 29 (Comm) (18 January 2010)
Posted By lanbuk.com
Habaş Sinai ve Tibbi Gazlar Isthisal Endüstri A.Ş. v Sometal S.A.L. [2010] EWHC 29 is a judgment from United Kingdom on 18 January 2010. Cite it as [2010] EWHC 29. Search it by the party names, the citation [2010] EWHC 29, or United Kingdom judgment.
To download the full judgment, go to the end of this page
What follows is the text read from the court's own file. The complete judgment is a PDF (500 KB), and the download button is at the foot of this page.
January 18, 2010
UNITED KINGDOM
Habaş Sinai ve Tibbi Gazlar Isthisal Endüstri A.Ş.
v.
Sometal S.A.L. [2010] EWHC 29
[2010] EWHC 29
Case brief
- Court
- United Kingdom
- Date
- 18 January 2010
- Citation
- [2010] EWHC 29
- Proceeding
- Judgment. United Kingdom.
- Principle
- An arbitration clause may be incorporated by a general reference to the terms of earlier contracts between the same parties. By lanbuk.com
Only what is recorded for this judgment is shown. · Browse cases by topic
Neutral Citation Number: [2010] EWHC 29 (Comm) Case No: 2009 FOLIO 1001 IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION COMMERCIAL COURT Royal Courts of Justice Strand, London, WC2A 2LL Date: 18/01/2010 Before : MR JUSTICE CHRISTOPHER CLARKE --------------------Between : HABAŞ SINAI VE TIBBI GAZLAR ISTHISAL ENDǕSTRI A.Ş.
Claimant
- and – SOMETAL S.A.L.
----------------------------------------Paul Key and Siddharth Dhar (instructed by Radcliffes Le Brasseur) for the Claimant John Russell (instructed by Clyde & Co) for the Respondent Hearing dates: 18th December 2009 --------------------Judgment
MR JUSTICE CHRISTOPHER CLARKE :
This is an application by Habaş Sinai ve Tibbi Gazlar Isthisal Endustri A.S. (“Habaş”) under section 67 of the Act 1996. Habaş, a Turkish company, seeks to set aside an Interim Final Award on and Costs made by an LCIA Arbitral Tribunal (“the Tribunal”) by which the Tribunal decided that it had jurisdiction to entertain the claim made by Sometal S.A.L (“Sometal”), a Lebanese company. On such an application the Court is not involved only in reviewing the decision of the Tribunal: Azov Shipping v Baltic Shipping Co (No 1) [1999] 1 Lloyd’s Rep
68. The underlying contract
By a contract in writing dated 9 th June 2008 (“the June Contract”), typed on a sheet of paper with the letter heading of a company whose abbreviated name is “Metkīm” (hereafter “Metkim”)1, Sometal S.A.L. (“Sometal”), for which Metkim acted as agent, agreed to sell 10,000 m.t. of steel scrap ex Romania & Bulgaria CIF FO Memrut Bay, Turkey. The contract contained a number of terms under the headings Material, Quantity, Price, Shipment, Discharge Rate, Payment, Final weight and NOR Tenderence (sic) and then ended with the words: “ALL THE REST WILL BE SAME AS OUR PREVOUS CONTRACTS”
The Issues
There had been 14 previous contracts between the same parties. The issues that presently divide them are whether general words such as these are capable of incorporating an arbitration clause and whether, if they are, the effect of these words as between these parties was to incorporate a London arbitration clause in the following terms: “All disputes, or controversies, or differences, which may arise between buyer and seller under this contract, shall be settled in London, according to London Arbitration Rules, by the United Kingdom Law”. I call this “the London arbitration clause”. The parties have agreed that, if this clause forms part of their contract, then the dispute between them, which is as to the validity of Sometal’s claim for more than US $ 5 million on account of Habaş’ alleged repudiation of the contract by failing to take delivery of the scrap, is to be resolved by an LCIA arbitration.
Habaş contends, firstly, that for a clause such as the London arbitration clause to be incorporated into a contract there must either be an express reference to the clause or wording that shows a clear intention to incorporate it, and that in the present case neither requirement is satisfied. Secondly, even if general words are capable of incorporating such a clause, the words used in the present case are inapt for the purpose. Sometal submits that there are no such requirements and that the Tribunal was right to find that the parties had intended to incorporate the London arbitration clause.
Metkim Metal Makina Kimya Sanayi Ve Dis Ticaret Limited Sirketi
The previous contracts
The first 3 of the previous 14 contracts were on paper with Habaş’ letter heading. The next 11 were either on a form drawn up by Sometal or on paper with Metkim’s letter heading.
The sequence of contracts was as follows. (i)
23 January 2004: a contract prepared by Habaş which provided: “Should any dispute arise during the conclusion or execution of this contract, the parties will endeavour to settle any disputes in amicable fashion. Should the parties be unable to reach an amicable solution, the disputes should be submitted to the Court of Arbitration with UNCITRAL Arbitration Rules”.
(ii)
24 May 2004: clause.
(iii)
5 September 2005: a contract prepared by Habaş which contained a clause in which the first sentence was as in the two previous contracts but in which the second sentence read:
a contract prepared by Habaş which contained the same
“Should the parties be unable to reach an amicable solution, the disputes shall be submitted to the Court of Arbitration in Istanbul according to the Turkish laws”. (iv)
23 March 2006: a two-page contract prepared by Sometal which contained the London Arbitration Clause as the second of two clause 10s.
(v)
14 March 2007: a one-page contract on Metkim’s letter heading which provided, after the operative clauses dealing with Material. Quantity, Price, Shipment, Payment etc: “The rest will be agreed mutually”
(vi)
3 May 2007: a contract like that of 23 March 2006 prepared by Sometal which contained the London Arbitration Clause.
(vii)
9 August 2007: a one-page contract on Metkim’s letter heading provided:
which
“The rest will be as per previous contracts” (viii)
11 September 2007: a one-page contract on Metkim notepaper, which also provided: “The rest will be as per previous contracts”.
(ix)
25 October 2007: A one-page contract on Metkim notepaper, which again provided:
“The rest will be agreed mutually” (x)
3 April 2008: A contract prepared by Sometal like that of 23 March 2006 which contained the London Arbitration Clause.
(xi)
9 April 2008: A contract prepared by Sometal like that of 23 March 2006 which contained the London Arbitration Clause.
(xii)
14 April 2008: A one-page contract, on Metkim notepaper, which provided: “The rest will be agreed mutually”
(xiii)
6 May 2008: there were two contracts with this date, which provided as follows: i. The first contract in time was on Metkim notepaper, was signed by Habaş on that date, and provided: “All the rest will be same as our previous contracts” ii. The second contract, prepared by Sometal, which was signed by at least one of the parties on 12 May 2008 and thus superseded the earlier contract, contained the London Arbitration Clause.
(xiv)
27 May 2008: a (one-page) contract, on Metkim notepaper, which provided: “All the rest will be same as our previous contracts”
(xv)
9 June 2008, the June Contract: a (one-page) contract, on Metkim notepaper which provided: “All the rest will be same as our previous contracts”
In respect of each of the contracts which provided that “The rest will be agreed mutually”, or “The rest will be as per previous contracts,” or “All the rest will be same as our previous contracts”, other than the first contract of 6 May 2008, there is no evidence of any later agreement that disputes should be determined by arbitration. The Metkim prepared contracts, like the Sometal prepared contracts set out the terms relating to Material, Quantity, Price and Shipment but, unlike the Sometal contracts, did not set out terms relating to quality, demurrage, force majeure or law and arbitration. The ruling of the Tribunal
The Tribunal (Sir Simon Tuckey, Chairman, Mr Mark Hamsher and Mr Stephen Jagusch) heard Habaş’ challenge to its jurisdiction as a preliminary issue. In paragraphs 13 and 14 of its Award it recorded the distinction made by the Courts
between (a) cases where what was sought to be incorporated were the terms of a separate contract between two other persons or between one of the parties and a third party, on the one hand, where, as it held, specific reference to the arbitration clause or demonstration of a clear intention to incorporate the arbitration clause was required, and (ii) other cases of incorporation where general words would suffice and where no specific evidence of clear intention to incorporate the arbitration clause was required. It then held that the present case fell into the latter and not the former category
On the issue as to whether the words used did in fact incorporate the London arbitration clause, the Tribunal referred to the fact that the June contract, like the other Metkim prepared contracts, did not refer to important commercial terms such as quality and demurrage and asked itself whether the reference to terms “as our previous contracts” should be limited to terms such as those, as Habaş contended. It answered that question in the negative, deciding that the intention of the parties was to incorporate any terms from previous contracts which added to the terms set out in the short form Metkim prepared contracts. It then defined the question that it had to answer as being: is it clear where one has to look to discover what those terms were?
The Tribunal then decided that the parties could not possibly have intended to refer back to the Habaş prepared contracts (contracts 1-3) because Metkim had not been involved in making those contracts, each of which was subject to Turkish law and the last of which had been made in September 2005. It then held that the parties could not have intended to refer to the previous Metkim prepared contracts because those contracts either contained no relevant additional terms at all (in the case of contracts 5, 9, and 12 where the terms were to be agreed) or themselves referred to previous contracts (in the case of contracts 7, 8, 13 and 14). That left only the Sometal prepared contacts, which contained additional terms including the London arbitration clause.
As a result, the Tribunal concluded, the parties, by incorporating “all the rest” of the terms in “our previous contracts” in the June Contract clearly intended to refer to the additional terms to be found in the Sometal prepared contracts. The Tribunal thought that, if there was any doubt about the matter, it was resolved by what happened in relation to contract
13. In that case a Metkim prepared contract providing “all the rest will be same as our previous contracts” was replaced by one including the London arbitration clause in circumstances where there was nothing to suggest that the second contract was intended to be a variation of the first. The inference that the Tribunal drew was that the parties intended and understood that, when Metkim referred to terms in previous contracts, it was referring to the additional terms in the fuller Sometal prepared contracts. There was no reason why the same words used in the June Contract should not have been intended and understood by the parties to have the same meaning. Are general words of incorporation sufficient?
The authorities recognise a distinction in approach between cases in which the parties incorporate the terms of a contract between two other parties or between one of them and a third party and those in which they incorporate standard terms.
Parties are free to incorporate (or seek to incorporate) whatever terms they choose by whatever method they choose. In those circumstances it is unwise to seek to formulate definitive categories. But, with that caveat, most attempts at incorporation of an arbitration (or jurisdiction) clause are likely to fall within one of the following broad categories (in which the terms referred to include an arbitration clause):
A and B make a contract in which they incorporate standard terms. These may be the standard terms of one party set out on the back of an offer letter or an order, or contained in another document to which reference is made; or terms embodied in the rules of an organisation of which A or B or both are members; or they may be terms standard in a particular trade or industry.
A and B make a contract incorporating terms previously agreed between A and B in another contract or contracts to which they were both parties
A and B make a contract incorporating terms agreed between A (or B) and C. Common examples are a bill of lading incorporating the terms of a charter to which A is a party; reinsurance contracts incorporating the terms of an underlying insurance; excess insurance contracts incorporating the terms of the primary layer of insurance; and building or engineering sub contracts incorporating the terms of a main contract or sub-sub contracts incorporating the terms of a sub contract
A and B make a contract incorporating terms agreed between C and D. Bills of lading, reinsurance and insurance contracts and building contracts may fall into this category.
Mr Paul Key on behalf of Habaş submits that no authority is to be found dealing with cases in category (ii) but that the same approach should be adopted in respect of such cases as in those in categories (iii) and (iv), namely that, in order for an arbitration clause to be validly incorporated there must either be a specific reference to the clause in the incorporating contract or that contract must manifest a clear intention to incorporate the arbitration clause in question. The Bill of Lading cases
In Thomas v Portsea [1912] AC 1 the House of Lords held that an arbitration clause in a charterparty between shipowner and charterer was not incorporated in a bill of lading contract between the shipowner and the holder of the bill in the absence of an express reference in the bill of lading not merely to the terms of the charterparty but specifically to the arbitration clause. The bill of lading had provided for the payment of freight “with other conditions as per charterparty with average accustomed” together with a manuscript clause reading:
“Deck load at shipper’s risk, and all other terms and conditions and exceptions of charter to be as per charter party, including clause”. Lord Loreburn LC said that the arbitration clause was not one which governed shipment or carriage or delivery and only governed “the way of settling disputes between the parties to the charterparty and disputes arising out of the conditions of the charterparty, not disputes arising out of the bill of lading” and that if the holders were to be put under “an obligation to arbitrate because that obligation is stated in the charterparty, it must be done explicitly”.
Lord Atkinson said that when it was sought to introduce into a document “like a bill of lading – a negotiable instrument – a clause such as this arbitration clause, not germane to the receipt, carriage, or delivery of the cargo or the payment of freight - the proper subject-matters with which the bill of lading is conversant - this should be done by distinct and specific words”. Lord Gorrell thought it unlikely that a consignee would assent to a clause which might commit him to arbitration at a port of shipment with which he had no connection and on the fact that if the arbitration clause was actually written into the bill of lading, it would be seen to be inconsistent with it. He said that “very clear language should be introduced into any contract” which was to have the effect of precluding parties from bringing a dispute before a court of law. Lord Robson doubted whether, when written out into the bill of lading the arbitration clause was applicable to a dispute between persons other than the parties to the charter and referred to the status of the bill of lading as a negotiable instrument as a reason for requiring that “if it is sought to deprive either party of his ordinary legal remedies, the contract cannot be too explicit and precise”.
That approach, namely that general words of incorporation in a bill of lading are not to be construed as incorporating the terms of a charterparty arbitration clause applicable to disputes under the charterparty was followed in The Annefield [1971] P 1682; The Varenna [1983] 2 Lloyd’s Rep 592; and The Federal Bulker [1989] 1 Lloyd’s Rep 103.
In The Federal Bulker [1981] 1 Lloyd’s Rep 103 the issue was whether a clause in a charterparty requiring bills of lading to provide for arbitration of “all disputes arising out of this contract” was incorporated in bills which provided “all terms …… as per charterparty …. to be considered as fully incorporated as if fully written”. The Court of Appeal held that the arbitration clause was not incorporated. Bingham LJ, as he then was, said:
Generally speaking, the English law of contract has taken a benevolent view of the use of general words to incorporate by reference
The judgments of Brandon, J, and of the Court of Appeal indicate, however, that general words of incorporation in a bill of lading may be effective to incorporate an arbitration clause where the arbitration clause in the charterparty applies both to disputes under the charterparty and the bill of lading: see The Merak [1965] P
223. But these propositions do not appear to be reconcilable with The Varenna and The Federal Bulker: see Siboti K/S v BP France SA [2003] EWHC 1278.
standard terms to be found elsewhere. But in the present field a different, and stricter, rule has developed, especially where the incorporation of arbitration clauses is concerned. The reason no doubt is that a bill of lading is a negotiable commercial instrument and may come into the hands of a foreign party with no knowledge and no ready means of knowledge of the terms of the charterparty. The cases show that a strict test of incorporation having, for better or worse, been laid down, the Courts have in general defended this rule with some tenacity in the interests of commercial certainty. If commercial parties do not like the English rule, they can meet the difficulty by spelling out the arbitration provision in the bill of lading and not relying on general words to achieve incorporation.
Citations and appeal history
Read from the judgments on Lanbuk: a link is shown only where a judgment's text carries the other's exact citation. The quotes are the court's own words, so you can see how the case was used.
No other judgment on Lanbuk is recorded as citing this one, and it cites none of them by citation. It may still be cited in judgments and reports that are not on Lanbuk.
Why is Habaş Sinai ve Tibbi Gazlar Isthisal Endüstri A.Ş. v Sometal S.A.L. important?
Habaş Sinai ve Tibbi Gazlar Isthisal Endüstri A.Ş. v Sometal S.A.L. is important for this principle: An arbitration clause may be incorporated by a general reference to the terms of earlier contracts between the same parties. The judgment is listed under United Kingdom on 18 January 2010.
How do I cite Habaş Sinai ve Tibbi Gazlar Isthisal Endüstri A.Ş. v Sometal S.A.L.?
Cite Habaş Sinai ve Tibbi Gazlar Isthisal Endüstri A.Ş. v Sometal S.A.L. as Habaş Sinai ve Tibbi Gazlar Isthisal Endüstri A.Ş. v Sometal S.A.L. [2010] EWHC 29, which is its recorded neutral or law-report citation. The decision is from United Kingdom on 18 January 2010.
Cite this page
Habaş Sinai ve Tibbi Gazlar Isthisal Endüstri A.Ş. v Sometal S.A.L. [2010] EWHC 29 (Lanbuk, 21 November 2026) <https://www.lanbuk.com/cases/habas-sinai-ve-tibbi-gazlar-isthisal-endustri-a-s-v-sometal-s-a--m39ci> accessed 24 November 2026