DVYN STRATEGIES LIMITED V SUNBIRD BIOENERGY (SL) LIMITED (MISC APP 2 of 2020) 2022 SLHCFTCAD 2 (30 June 2022)

Posted By lanbuk.com

DVYN STRATEGIES LIMITED V SUNBIRD BIOENERGY is a judgment from Sierra Leone on 30 June 2022. Search it by the party names, or Sierra Leone judgment.

Sierra Leone — High CourtPDF · 476 KBJudgment

To download the full judgment, go to the end of this page

What follows is the text read from the court's own file. The complete judgment is a PDF (476 KB), and the download button is at the foot of this page.

June 30, 2022

SIERRA LEONE — HIGH COURT

DVYN STRATEGIES LIMITED

v.

SUNBIRD BIOENERGY

Case brief

Court
Sierra Leone — High Court
Date
30 June 2022
Proceeding
Judgment. Sierra Leone.

No headnote or brief is recorded for this judgment yet, so none is shown. Read the judgment below for the facts, the issues and what the court decided.

Only what is recorded for this judgment is shown. · Browse cases by topic

FTCC MISC.APP 005/20 2020 D. NO. 2

IN THE HIGH COURT OF SIERRA LEONE COMMERCIAL AND ADMIRALTY DIVISION IN THE MATTER OF A CONSULTANCY AGREEMENT BETWEEN DYVN STRATEGIES LIMITED AND SUNBIRD BIOENERGY (SL) LIMITED AND IN THE MATTER OF A JOINT VENTURE AGREEMENT BETWEEN DVYN STRATEGIES LIMITED AND SUNBIRD BIOENERGY (SL) LIMITED

BETWEEN:

DVYN STRATEGIES LIMITED

AND

SUNBIRD BIOENERGY (SL) LIMITED

COUNSEL:

B. Jones Esq for the Plaintiff/

A. B. Bangura Esq for the Defendant/

JUDGMENT DELIVERED THIS 30th DAY OF June 2022 BY THE HON. JUSTICE F. BINTU ALHADI J.A, (Sitting as a High Court Judge),

Judgment of Hon. Justice F. Bintu Alhadi in Dvyn Strategies Ltd v Sunbird Bioenergy (SL) Ltd. 1

Judgment

1. On the 12th of February 2021 an application was made to the Court by way of Originating dated the 5th day of March 2020 by Dvyn Strategies Limited, the Plaintiff/ Applicant against Sunbird Bioenergy (SL) Limited, the Defendant/Respondent, praying for the following Orders:

i) That the Defendant do immediately pay the Plaintiff the Leones equivalent of the sum of US$165,670.00 (One Hundred and Sixty Five Thousand Six Hundred and Seventy United States Dollars) due and owing the Plaintiff under Consultancy Agreement dated 3rd October

ii) That the Defendant do immediately pay the Plaintiff the Leones equivalent of the sum of US$417,900 (Four Hundred and Seventeen Thousand Nine Hundred United States Dollars) being sum due from the Defendant under a Joint Venture Agreement dated 21st October

iii) Interest

iv) Any further Order(s)/relief (s) that this Honourable Court may deem fit and just.

v) That the costs of and incidental to this action be provided for and that the same be borne by the Defendant.

2. The application was supported by the of Oluniyi Robbin-Coker of No 12 Main Main Motor Road, Congo Cross, Freetown in the Western Area of the Republic of Sierra Leone and sworn to on the 5th of March 2020 together with 8 exhibits attached thereon.

3. Counsel for the Defendant/Respondent, A. B. Bangura Esq, filed an affidavit in opposition sworn to by Mr. Karpagam Govindaswany Kandaswamy, the newly installed Chief Executive Officer of Sunbird Bioenergy (SL) Limited on the 21st day of July 2020.

Judgment of Hon. Justice F. Bintu Alhadi in Dvyn Strategies Ltd v Sunbird Bioenergy (SL) Ltd. 2

4. Summary of the Plaintiff’s Case

a. The Plaintiff avers that the Defendant offered it a consultancy that commenced on the 3rd of October 2016 for the provision of inter alia Government relations and management services. (Exhibit A) He said that the key terms of the offer were as follows: b. That the tasks to be performed will be agreed upon on a quarterly basis. c. That the consultancy rate per day is US$1,000 (One Thousand US Dollars) subject to annual review. d. That the services of the Plaintiff will be retained for 25 days per quarter. e. That the agreement will subsist until terminated in writing by a 90 days’ notice. f. That the Defendant will pay the Plaintiff the sum of US$ 100,000 (One Hundred Thousand Dollars) for work done and expenses. g. That the Defendant will further pay the Plaintiff the sum of US$25,000 (Twenty-Five Thousand US Dollars) for the completion of the Deed of Variation.

5. According to the Plaintiff, this offer was accepted and communicated by letter to the Defendant on the 6th day of October 2016. (Exhibit B) Invoices were then issued to the Defendant in respect of the consultancy services, prior work, and completion of the Deed of Variation. Payment on the invoices were not met despite promises made by the erstwhile general manager and the finance manager to pay. (Exhibit D and E) ( In July 2018, the Defendant acknowledged the indebtedness through its new director, Andrew Gee Exhibit F).

6. Furthermore, the Plaintiff stated that it had a joint venture arrangement comprising “Binding and Irrevocable Heads of Terms" with the Defendant dated 21st October 2016. (Exhibit G) That based on the meter units billed by the Defendant for the periods 2017 and 2018 and the revenue sharing formula contained in the joint venture agreement, the Plaintiff became entitled to the sums of US$ 138,770 for the calendar year of 2017; and the sum of US$ 279,130 for the calendar year of 2018. (Exhibit H).

7. Invoices based on the sums due under the joint venture agreement were also not honoured.

Judgment of Hon. Justice F. Bintu Alhadi in Dvyn Strategies Ltd v Sunbird Bioenergy (SL) Ltd. 3 Summary of the Defendant’s Case

8. In his affidavit in opposition, the newly installed Chief Executive Officer of Sunbird Bioenergy (SL) Limited, on behalf of the Defendant, averred that the erstwhile management of the Defendant company entered into a consultancy agreement with the Plaintiff consultant entity commencing 3rd October 2016 for the provision among others of Government relations and management services generally related to the restart, operations, and expansion of the Defendant's bioenergy plant in-country.

9. The assignment description of the Plaintiff constituted specific tasks to be performed by the Plaintiff for the period ending December 2016. These were as follows: a. Assistance to obtain the necessary comfort letters. b. Assistance to obtain a letter from the Ministry of Energy requesting for power to be supplied in January 2017. c. Assistance to open letter of credit (L/C) for power. d. Assistance to settle the tariff of the PPA from years 11 to 20 years. e. Assistance to extend the tax incentive agreement. f. Assistance to negotiate an increase in the increased offtake or power under the PPA. g. Assistance with engaging the Government of Sierra Leone for Sunbird’s participation in Magbass.

10. These were not reviewed after the 31st of December 2016 for the Plaintiff's engagement and performance. The Defendant averred that the Plaintiff failed to assist the Defendant get expected outcomes in his government relations and management service duties. He said that the Defendant was dissatisfied with the lack of progress with the Electricity, Distribution and Supply Authority (EDSA) on the very issues for which the Plaintiff was consulted and contracted.

11. These include among others the failure by EDSA/Government to open letters of credit in favour of the Defendant in respect of payment for supplied energy to the national grid and the continuing failure of the Government to make the agreed payments for electricity supplied without unconscionable delays. Exhibit KGK 1 A-H shows the letters between the Defendant and the Government and energy sector-wide players on issues touching the Plaintiff's assignment description.

12.The Defendant argued that the invoices (exhibits C 1-6) were not in place or earned and were not honoured. That Exhibits D and E in paragraph 6 of the Plaintiff’s affidavit do not go to the root of the issue of liability raised by the Plaintiff. He said that exhibit F of the Plaintiff’s affidavit, which is a letter Judgment of Hon. Justice F. Bintu Alhadi in Dvyn Strategies Ltd v Sunbird Bioenergy (SL) Ltd. 4 of 13th July 2018, was orally requested by the managing director of the Plaintiff company to help him provide comfort to his bankers and was never actually a reflection of the reality between the Plaintiff and the Defendant. (Exhibit KGK 2 - copy of email of Andrew C. H. Gee, then Director of the Defendant, on the issue.)

13. He said that the Plaintiff and the Defendant further had a joint venture understanding to provide all necessary local government relations that will facilitate the restart, operation, and future expansion of the Defendant's project in Sierra Leone. The understanding was to be converted into a substantive agreement within 180 days from the 21st of October, it was the parties’ understanding, inter alia, that:

(a) The joint venture shall be structured on a revenue sharing basis.

(b) The revenue share shall be calculated using the formula of $0,01 per KWh of electricity that is purchased and paid for by the Government of Sierra Leone whilst the plant is operating within its design specification (e.g., total power generation is by utilisation of biomass), at the current PPA tariff of $0.20c per KWh.

(c) The Plaintiff will assist the Defendant with timely payment for power, etc.

14. He said that the Plaintiff is by no means entitled to the sums of $138,770.00 and $279,130.00 for the calendar 2017 as claimed by reason of the fact that tariff calculation of $20c per KWh was not sustained in addition to the Plaintiff’s failure to assist the Defendant with timely payment for power. The meter billing marked exhibit H referred to by the Plaintiff, is not correct and emanated not from the Defendant. (Exhibit KGK 3) a copy of the record of analysis of EDSA’s payment trend showing the inordinate payment delays which are outside the spirit of the joint venture understanding of the parties.

15. That the failure of the Plaintiff to assist the Defendant in its crucial phase of restarting, operating, and expanding its project as provided for in the consultancy agreement and their understanding has caused the Defendant great hardship.

The Defendant pray that the Orders prayed for by the Plaintiff are unconscionable and should be discountenanced in the interest of equity and justice.

Judgment of Hon. Justice F. Bintu Alhadi in Dvyn Strategies Ltd v Sunbird Bioenergy (SL) Ltd. 5 DECISION OF THE COURT

Analysis of the law and evidence

16.1 have considered the application before the court together with its affidavit in support and exhibits attached thereon; the affidavit in opposition and its exhibits attached thereon as well as the oral and written submissions made by both counsel.

17. The questions that arise are twofold: Firstly, was there a contract? What does a contract mean in law? The most basic definition of a contract in law is, that it is a promise or set of promises which the law will enforce; Pollock, Principles of Contract 13th edition [19501 at o

1. Or ‘it is an agreement giving rise to obligations which are enforced or recognised by law;' Trietel, The Law of Contract, 11th edition [20031 at p.

1. In other words, these are promises between parties, mutual obligations created thereby and the rights that emanate from the fulfilment of the promises.

18. Counsel for the defendant submitted that, for there to be a binding contract between the parties, there must be an offer and an acceptance, and for the acceptance to be valid, it must mirror the exact terms of the offer, and no more or less. Furthermore, he relied on Cheshire, Fifoot and Furmston, “Law of Contract” 16th edition at page 11 which stated that, “whatever the difficulties and however elastic their rules, the judges must, either upon oral evidence or by the construction of documents, find some act from which they can infer the offeree’s intention to accept, or they must refuse to admit the existence of an agreement. “

19. “This intention, moreover, must be conclusive. It must not treat the negotiations between the parties as still open to the process of bargaining. The offeree must unreservedly assent to the exact terms proposed by the offeror. If while purporting to accept the offer as a whole, he introduces a new term which the offeror has not had the chance of examining, he is, in fact merely making a . The effect of this in the eyes of the law is to destroy the original offer.”

Judgment of Hon. Justice F. Bintu Alhadi in Dvyn Strategies Ltd v Sunbird Bioenergy (SL) Ltd. 6

20. From the facts of the case, exhibit A of the affidavit in support which is an offer letter addressed to the Plaintiff herein from the Defendant, stated the terms of the consultancy agreement as stated on pages 3 and 4 under the heading “Summary of the Defendant’s case." It amounts to an offer letter from the defendant, Sunbird Bioenergy (SL) Limited dated 3rd October 2016. The subject matter of the said letter is “Consultancy Agreement."

21.lt read in this way: “....Sunbird Bioenergy Africa would like to offer you a consultancy engagement commencing on today’s date to provide Government relations and management services to Addax Bioenergy Sierra Leone (to be renamed Sunbird Bioenergy Sierra Leone in Q4) we shall agree the exact tasks on a quarterly basis.. I understand that your consultancy rate is $1,000 per day. Sunbird Bioenergy would like to retain your services for 25 days per quarter. “

22. When the Plaintiff, Dvyn Strategies Limited replied, which is Exhibit B of the affidavit in support, dated 6,h October 2016, it stated inter alia that “ I hereby accept the consultancy assignment per the said letter and confirm the terms of compensation as follows: “a signature bonus in of prior work of US$100,000 to be paid immediately; bonus for deed of variation US$25,000 to be paid on completion of deed of variation; quarterly compensation assuming 25 day per quarter at discounted rate of US$1,000 per day to be paid quarterly in advance."

23. By doing this, the Plaintiff destroyed the original offer, or it rejected the original offer; Hyde v Wrench.... which could be referred to as a purported acceptance of the offer, it did not mirror the exact terms of the offer and it was not unequivocal. It did not unequivocally assent to the exact terms offered by the defendant/offeror. The reply, the said exhibit B, introduced new terms. By stating such terms that did not mirror the exact terms of the offer, the plaintiff introduced new terms, and this could be described as a counter-offer."

Judgment of Hon. Justice F. Bintu Alhadi in Dvyn Strategies Ltd v Sunbird Bioenergy (SL) Ltd. 7

24. In this respect, I cannot say that there was a valid and binding contract between the parties; United Dominions (Commercial) Limited v Eagle Aircraft Services Limited (1968] 1 WLR

74. I cannot say that it was an acceptance of the offer. The plaintiff, Dvyn Strategies Limited, did not unequivocally assent to the exact terms offered by the offeror.

25.Secondly, assuming that there was a contract, did consideration move from the promisee/offeree? Did the plaintiff perform its own side of the bargain? For a contract/agreement to be deemed legally binding, there must be consideration on the part of every person or company who enters the contract. Consideration is the benefit that each party gets or expects to get from the contractual agreement. In other words, each party gives up something in exchange. When a contract lacks consideration, the court could step in and declare that a contract is unenforceable because it lacks

Citations and appeal history

Read from the judgments on Lanbuk: a link is shown only where a judgment's text carries the other's exact citation. The quotes are the court's own words, so you can see how the case was used.

No other judgment on Lanbuk is recorded as citing this one, and it cites none of them by citation. It may still be cited in judgments and reports that are not on Lanbuk.

Judges

The judges named in this report. Each page lists their other judgments on Lanbuk.

Counsel

The lawyers who appeared, as named in the judgment.

  • B. Jonesfor the Plaintiff/Applicant
  • A. B. Bangurafor the Defendant/Respondent

Cite this page

DVYN STRATEGIES LIMITED V SUNBIRD BIOENERGY (Lanbuk, 15 November 2026) <https://www.lanbuk.com/cases/dvyn-strategies-limited-v-sunbird-bioenergy-sl-limited-misc-app--155yy> accessed 23 November 2026

The accessed date is today's date. Check your course or publisher's style guide.

Community discussion

Community discussion is for learning only and is not legal advice. Never share client or confidential information. See the community guidelines.