Bremer Vulkan Schiffbau und Maschinenfabrik v South India Shipping Corporation Ltd
1981 · [1981] AC 909
Posted By lanbuk.com
- Facts
- South India Shipping bought ships from Bremer Vulkan, a German shipbuilder, under contracts with clauses. It started arbitration alleging defects, but then allowed the claim to lie dormant for years. Bremer Vulkan asked the court for an to stop the arbitration for want of prosecution.
- Issue
- Could the court, or the arbitrators, end an arbitration because the claimant had delayed for an inordinate time?
- Held
- No. The House of Lords held that the court had no general power to supervise the conduct of an arbitration by injunction. The arbitrators had the same duty as the claimant to keep the arbitration moving, and both parties were obliged to ask the arbitrators for directions to end the delay. The arbitrators had no power to dismiss the claim for want of prosecution.
- Principle
- At common law, neither the court nor the tribunal could dismiss an arbitral claim for delay. Both parties shared a duty to move the arbitration forward.
- Why it matters
- The decision left tribunals unable to deal with stale claims. Parliament in England later gave arbitrators that power, and section 51(2) of the 2022 Act gives it to tribunals in Sierra Leone.