
Civil appeal
Mendekia v Beresford-Cole (CIV APP 12 of 1972) [1973] SLCA 6 (11 July 1973)
Mendekia v Beresford-Cole is a civil appeal from Sierra Leone on 11 July 1973. Cite it as [1973] SLCA 6. Search it by the party names, the citation [1973] SLCA 6, or Sierra Leone civil appeal.
Sierra Leone — Court of AppealPDF · 997 KB[1973] SLCA 6Civil appeal
July 11, 1973
IN THE COURT OF APPEAL
Mendekia
Appellant
v.
Beresford-Cole
Respondent
CIV APP 12 of 1972
[1973] SLCA 6
Proceeding. Civil appeal. Sierra Leone.
SECTION 40
MENDEKIA v. BERESFORD-COLE, 1972-73 ALR S.L. 321
C.A.
before him, for depriving him of his costs out of the estate. A
piece of the respondent's evidence referred to by the learned
judge in his judgment is not only curious but telling. The respon
dent said:
"I am of the opinion that it is desirable for letters of admin- 5
istration to be gran ted to me instead of the Administrator-
General in the light of previous court proceedings I have
referred to. It is because although I bought property from
the deceased she did not transfer the same to me, that I am
of the opinion that. it is desirable for letters of administra- 10
tion to be granted to me."
I, for my part, taking all the circumstances into consideration,
would deprive the respondent of his costs out of the estate and
order that he bears his own costs in this court and the courts
b~ow. 15
Order accordingly.
MENDE KIA v. BERESFORD-COLE
Court of Appeal (Percy Davies and Tejan, JJ. A. and
Rowland Harding, J.): July 11th, 1973
(Civil App. No. 12/72)
[ 1] Agency-characteristics of relationship-relationship exists when
''principal" authorises "agent" to represent him and affect his legal
relations with third parties: The relationship of agency exists between
two persons when one, the principal, expressly or impliedly authorises
the other, the agent, to represent him and affect his legal relations
with third parties (page 329, line 27- page 330, line 5).
[ 2] Building Contracts, Architects and Engineers-damages-measure of
damages-difference between agreed price and actual cost of completing
contract work: The measure of damages for failure by a contractor to
complete a building or engineering contract is the difference between
the agreed contract price and the actual cost of completing the contract
work (page 334, lines 15-20).
[ 3] Building Contracts, Architects and Engineers-implied terms-time of
performance-time not of essence in absence of contrary express words
if not of essence, employer's remedy for late completion damages not
repudiation: In the absence of express words making time of the essence
of a building contract the contractor's failure to complete work within
the time specified will not amount to such a breach as would release
the employer from the contract although it may entitle him to damages
(page 332, lines 15-20).
321
20
25
30
35
40
5
10
15
20
25
30
35
40
THE AFRICAN LAW REPORTS
[ 4] Contract-damages-measure of damages-breach of building contract
difference between agreed price and actual cost of completing contract
work: See [2] above.
[ 5] Contract- .. ·frustration-contract not frustrated if more onerous but only
if nature of work altered-provision for frustration by delay not appli
cable when delay wholly abnormal: The mere fact that as a result of an
unexpected tum of events the obligations of one of the parties to a con
tract are made more onerous than he anticipated is not sufficient to
invoke the doctrine of frustration unless the unforeseeable event actually
alters the nature of the work to be done, although if provision is made
for the suspension of the contract in the event of delay, it is read as
limited to normal moderate delay and does not extend to an inter
ruption that is so abnormal as to differ in kind from anything that
could have been contemplated (page 333, lines 4-32; page 333, line 36
-page 334, line 5).
[ 6] Contract-implied terms-building contracts-time not of essence in
absence of contrary express words--if not of essence employer's remedy
for late completion damages not repudiation: See [ 3] above.
[ 7] Documents-interpretation-document to be interpreted as a whole
words construed as they stand but context and object of agreement to
be considered when determining intention of parties: Although it is a
rule of interpretation that words should be construed as they stand, the
context and object of the agreement should also be considered when
determining the intention of the parties (page 330, lines 29-40).
[8] Time-performance-building contracts-time not of essence in absence
of contrary express words: See [3) above.
The appellant brought an action against the respondent in the
High Court for damages in respect of losses arising from the res
pondent's failure to complete a building contract. The respondent
counterclaimed for the expenses incurred by him over and above
the agreed contract price paid to him by the appellant.
The appellant bought a plot of land from the respondent who
agreed to build four flats on it for him. An agreement was ex
ecuted and the appellant paid to the respondent the total agreed
cost of the building work, which was to be completed in six
months. The agreement referred to the respondent as the appel
lant's agent but nothing else in the document gave the respondent
authority to affect the appellant's legal position in relation to a
third party.
The respondent engaged a contractor to carry out the work but
he failed to complete the building in the time stipulated; the
appellant agreed to allow a further month for the work, but it was
still not completed. The respondent then told the appellant that
322
MENDEKIA v. BERESFORD-COLE, 1972-73 ALR S.L. 321
C.A.
he had spent Le7000 on the construction work in excess of the
contract price and asked him to pay this additional amount before
the building was handed over.
After various delays and an attempted compromise, during
which the building remained unfinished, the appellant instituted 5
the present proceedings against the respondent claiming the
estimated cost of completing the work, loss or rents resulting from
the delay in completion and the amount of the professional fees
paid to a quantity surveyor for the assessment of the cost of com-
pletion. 10
The respondent counterclaimed for the amount spent by him
on construction in excess of the contract price.
The High Court (During, J.) found that the relationship be
tween the parties was that of principal and agent and that their
agreement did not constitute a contract. He dismissed both the 15
claim and counterclaim.
On appeal the appellant contended that the trial judge erred
in law in holding that the document executed by the parties did
not constitute a valid contract. He maintained that a contractual
relationship did exist, that the respondent's failure to complete 20
in the agreed time constituted a breach of its terms and that the
appellant was therefore entitled to damages for breach of contract.
In reply the respondent argued that the relationship between the
parties was that of principal and agent and the document merely
a receipt for the money paid by the appellant. There was in those 25
circumstances no breach of contract by the respondent entitling
the appellant to damages. The respondent further argued that his
failure to complete the building work was in any case due to the
rising costs of labour and materials and the court considered
whether in these circumstances the contract could be said to have 30
been frustrated, with the consequence of releasing the respondent
from his undertakings.
For procedural reasons, the respondent's appeal against the
dismissal of his counterclaim was held to be not properly before
the court. 3 5
The appellant's appeal was allowed and the respondent ordered
to pay damages for breach of contract.
Case referred to:
(1) British Movietonews Ltd. v. London & District Cinemas Ltd., [ 1952] 40
A.C. 166; [1951] 2 All E.R. 617.
323
5
10
15
20
25
30
35
40
THE AFRICAN LAW REPORTS
> ' '
(2) Davis Contractors Ltd. v. Fareham U.D.C., [1956] A.C. 696; [1956] 2
All E.R. 145, applied.
(3) Mertens v. Home Freeholds Co., [1921] 2 K.B. 526; (1921), 125 L.T.
355, applied.
(4) Parkinson (Sir Lindsay) & Co. Ltd. v. Commrs. of Work, [1949] 2 K.B.
632; [1950] 1 All E.R. 208, dicta of Asquith, L.J. applied.
(5) Smith v. Lucas (1881), 18 Ch. D. 531; 45 L.T. 460.
Minah for the appellant;
Marcus-Jones for the respondent.
TEJAN, J.A., delivering the judgment of the court:
This appeal is against the judgment of During, J. dated April
lOth, 1972. The facts in the case are that some time in 1968, the
appellant went to the respondent who sold two properties to him.
One property was a house at the Maize, Wilberforce and the other
was a plot of land ~t Kissy By-Pass. The appellant's case is that
when he bought the land at Kissy By-Pass, the respondent, who
represented himself as a contractor, volunteered to erect a build
ing on the land for the appellant. In order to assure the appellant
that he was a building contractor, the respondent showed to the
appellant several houses which he alleged that he built. He also
pointed out some men whom he said, were his workmen. On the
faith of this assurance, the appellant agreed that the respondent
should build a house for him on the land, and he then told the
respondent that he had with him the sum of Le14,000. The res
pondent told the appellant that the sum of Le14,000 was not
enough to build a big house which could be let at a profit. At the
suggestion of the respondent, the appellant agreed that the respon
dent should build certain blocks of flats and other buildings as
described in a plan submitted to the appellant by the respondent.
An agreement for the buildings was then executed. After the
execution of the agreement the appellant paid the sum of Le14,000
to the respondent and later paid the sum of LelO,OOO, making a
total sum of Le24,000, the agreed cost of the buildings. The appel
lant made it known to the respondent that he intended to let out
the houses, the building of which the respondent failed to complete
in accordance with the terms contained in the agreement dated
December 3rd, 1968, which is as follows:
''Received the sum of Le14,000 (fourteen thousand leones)
from Sahr Lebbie Mendekia Esq., farmer, of 27 Yaradu Road,
324
MENDEKIA v. BERESFORD-COLE.1972-73 ALR S.L. 321
C.A.
Koidu Town, Kono District in the Eastern Province of Sierra
Leone being part payment of the sum of Le24,000 (twenty
four thousand leones) for the costs of construction of a
two-storey building with boys' quarters and a car port on
1907 acres of land situated off Kissy By-Pass Road, Kissy 5
Village,_ as more fully described and delineated on the
Director of Surveys and Lands Plan LS. 1070/68 dated
November 28th, 1968 to be build and constructed with the
best labour and materials available within a maximum period
of 6 (six) calendar months from the date hereof; the said 10
structures to contain the following:
Two-Storey Building: Four self-contained semi-detached
flats:
Ground Floor: Flat No. 1 -lounge and dining room, two
bedrooms, one bath and water closet, kitchen: Estimated 15
unit cost- Le4,400;
Flat No. 2 -lounge cum dining room, three bedrooms,
one bath and water closet, kitchen: Estimated unit cost -
Le4,400.
First Floor: Flat No. 3- -lounge cum dining room, two 20
bedrooms, one bath and water closet, kitchen: Estimated
unit cost- Le4,400;
Flat No. 4 -lounge cum dining room, three bedrooms,
one bath and water closet, kitchen: Estimated unit cost -
Le6,600. 25
Boys' Quarters & Car Port: Boys' Quarters - two bedrooms,
one water closet and shower;
car port - covered accommodation for four cars: Estimated
unit cost - Le200.
Exigencies - Le800 30
Total costs - Le24,000
I, Sahr Lebbie Mendekia aforesaid, for myself, my heirs
and successors in title do hereby contract and agree with my
agent George Beresford-Cole, Real Estate Agent, of 23
Liverpool Street, Freetown, Sierra Leone to pay to him the 35
balance of Le10,000 (ten thousand leones) in full, on or
before but not later than February 28th, 1969 for the ful-
filment of the purpose hereinbefore contained."
When the respondent failed to complete the buildings within
the period stipulated in the agreement he requested the appellant 40
to give him a further month within which further period he could
325
THE AFRICAN LAW REPORTS
complete the buildings. The respondent was given the requested
one month but he still failed to complete the building. He then
told the appellant that he had spent the sum of Le7 ,000 out of
his own pocket. When the appellant demanded the key to the
5 buildings, the respondent refused to hand over the key to him.
The respondent said that he would hand over the key after the
appellant had refunded the sum of Le7 ,000.
The respondent's case is that in the latter part of 1968, a
police officer by the name of Y andeman introduced the appellant
10 to him for the purpose of buying property. The appellant bought
one property at the Maize, Wilberforce and a plot of land off the
Kissy By-Pass Road. In the process of doing business, the respon
dent and the appellant became friendly, and while on that friendly
basis, the appellant wanted to know who built the respondent's
15 houses at Goderich and Liverpool Street. The respondent told the
appellant that he designed and supervised the buildings with local
contractors. The appellant then said he wanted a building erected
on the plot of land he bought from the respondent, and that he
wanted a similar design to the respondent's building at Liverpool
20 Street. The respondent advised the appellant to build flats instead.
The appellant agreed to build the flats and the respondent under
took to supervise the building of the flats. On December 3rd,
1968, the appellant made part payment to the respondent of the
sum of Le14,000 for the building of the flats. The appellant and
25 the respondent then made a rough estimate of costs and agreed
on the unit value of the various items that were to be included
in the construction. The appellant being illiterate, a police officer,
Y andeman, acted on his behalf. The respondent, after signing
the agreement said he engaged a contractor by the name of Mr.
30 F.J. Turner of 30 Benjamin Lane, for the construction of the flats.
In June 1969, because of rising costs, the respondent realised
that he could not comply with the terms and conditions of the
agreement. The respondent wrote a letter to the appellant through
Yandeman and in October 1969, the respondent received a letter
35 from the appellant's solicitor. In the same month of October
1969, the respondent replied to the solicitor's letter. Later the
respondent saw the appellant in his office. The appellant told the
respondent that he did not like litigation and said that he would
return to Kono to see how best he could raise money for the
40 completion of the buildings. Some time after, the appellant came
again to the respondent's office, and suggested that the building
326
MENDEKIA v. BERESFORD-COLE,1972-73 ALR S.L. 321
C.A.
and land should be sold by the respondent, and that after the sale,
the sum of Le24,000 already paid by him plus the sum of Le2000,
the cost of the land, should be paid to him out of the proceeds of
the sale. The respondent asked the appellant to put in writing his
suggestion. In consequence of this, the respondent received a 5
letter dated December 29th, 1969 from the appellant's solicitor.
The respondent replied to it. After an interchange of letters
between the respondent and the appellant's solicitor, a writ of
summons was ultimately issued. In the amended statement of
claim the appellant claimed- 10
"(1) Special damages:
(a) Le17,455 which is the estimated cost of com
pleting the said building, boys' quarters and car port;
(b) Le4,800 representing loss of rent from June 3rd,
1969 to February 29th, 1971, i.e. 20 months at 15
Le240 per month (i.e. four flats at Le60 per month
per flat) and still continuing;
(c) Le500 being professional fees for valuing the un
finished work on the said building.
(2) General damages. 20
(3) Costs."
The respondent also filed a statement of defence and counter
claim.
In his judgment, During, J. dismissed the claim and counter
claim, and it is from this judgment that the appellant has now 25
appealed to this court on the following grounds:
( 1) That the learned trial judge erred in law in holding that the
document dated December 3rd, 1968, does not constitute a valid
contract.
(2) That the verdict is unreasonable and cannot be supported 30
having regard to the evidence before the court.
The respondent also filed a respondent's notice asking that the
decision of the court below should be varied by an order that the
appellant should pay to the respondent the claims on the counter-
claim on the following grounds: 3 5
1. That the learned trial judge having found against the plaintiff
on his claim ought to have upheld the defendant's counterclaim
because:
(a) There was sufficient evidence in support of the counterclaim
in respect of the various sums alleged to have been expended 40
by the defendant on the premises, which evidence remained
327
THE AFRICAN LAW REPORTS
unshaken and incontroverted throughout the whole of the
case.
(b) There was no necessity in law or in fact for the defendant to
obtain the prior permission of the plaintiff before expending
5 these monies.
(c) That by holding otherwise the plaintiff is inequitably and
unjustly enriching himself at the expense of the defendant.
2. That on the balance of the probabilities the evidence of the
defendant and his witnesses was the more credible and ought to
10 have been upheld as a sufficient discharge of the burden of proof
cast upon the defendant in respect of the said counterclaim.
On March 20th, 1973 when this appeal came before this court,
Mr. Minah, counsel for the appellant submitted that the court
ought not to hear the respondent's appeal on the ground that it
15 was not properly before the court. After having heard arguments
from both counsel, the court decided that the respondent having
failed to comply with r.20(1) and (2) now r.l7(1) of the Sierra
Leone Court of Appeal Ru1es, 1973 the respondent's notice was
not properly before the court.
20 In arguing Ground 1 of the appeal, Mr. Minah, after reviewing
the basic essentials necessary for the creation of a contract, main
tained that the document dated December 3rd, 1968 created a
contractual relationship between the appellant and the respondent.
In referring to the document in his judgment, During, J. said:
25 "I have read Exhibit C carefully and I hold that on a true
construction of the whole paper writing, it does not contain
a contract as alleged by the plaintiff in his statement of claim.
The relationship between the plaintiff and the defendant as
disclosed in the paper writing was one of principal and agent
30 in my judgment, on a true and proper interpretation of the
document and moreso on the evidence before me."
Dr. Marcus-Jones replied at length to the argument of Mr.
Minah. Before I deal with the arguments presented by Dr. Marcus
Jones I think it is necessary to state that on May 16th, 1973 when
35 Dr. Marcus-Jones was to complete his argument, he was absent
from court. [The learned justice of appeal explained what had
occurred and continued:] The court, having considered certain
factors apparent at the time ruled that in the circumstances the
respondent's case was regarded as closed.
40 However, in answer to Mr. Minah, Dr. Marcus-Jones insisted
328
MENDEKIA v. BERESFORD-COLE. 1972-73 ALR S.L. 321
C.A.
that the evidence disclosed the relationship between the appellant
and the respondent was that of a principal and agent, and he
maintained that the document dated December 3rd, 1968 was not
a contract but a receipt issued by the respondent for the sum of
Le14,000 received by the respondent from the appellant. 5
It seems to me that the first question to be determined is
whether the evidence and the document create the relationship
of agent and principal between the respondent and the appellant.
I shall first refer to the evidence at the trial. According to the
appellant, the respondent showed him some houses which he 10
alleged he had built and even showed him his workmen. He said
that the respondent agreed to build the four flats for him. The
respondent, on the other hand, said that he told the appellant that
he designed and supervised the buildings at Goderich and Liverpool
Streets, and that when the appellant expressed his desire to have 15
a building erected on the plot of land which he bought from the
respondent, he (the respondent) agreed to undertake the super
vision of the construction of the flats. When the appellant and the
respondent had come to an agreement as to the price, the respon-
dent then drew up the agreement dated December 3rd, 1968 20
which he signed. The respondent said that one P .C. Y andeman
acted on behalf of the appellant since the appellant was an illiterate.
The respondent further said that he engaged a contractor by the
name of Mr. Turner of 30 Benjamin Lane for the construction of
the flats. It is surprising that Yandeman and Mr. Turner were not 25
called to give evidence.
"Agency is the relationship that exists between two persons
when one, called the agent, is considered in law to represent
the other, called the principal, in such a way as to be able to
affect the principal's legal position in respect of strangers to 30
the relationship by the making of contracts or the disposition
of property."
See Fridman, Law of Agency, 2nd ed., at 8 (1966). According
to Bowstead on Agency, 13th ed., at 1 (1968):
"Agency is the relationship that exists between two persons, 35
one of whom expressly or impliedly consents that the other
should represent him or act on his behalf, and the other of
whom similarly consents to represent the former or so to act.
The ·one who is to be represented or on whose behalf the act
is to be done is called the principal. The one who is to 40
represent or act is called the agent."
329
THE AFRICAN LAW REPORTS
An agent is a person who is authorised to act for a principal and
has agreed so to act, and who has power to affect the legal rela
tions of his principal with a third party. In the case of agency,
there must be an authority to act. The agent has the authority
5 to affect the principal's legal relations with the outside world.
In the present case, there is no evidence that the respondent
had the authority to affect the appellant's legal relations with a
third party. The learned trial judge did not refer to the evidence
which led him to the conclusion that the relationship between the
10 appellant and respondent "was one of principal and agent." There
is no evidence that Mr. Turner the alleged contractor knew the
appellant or that the appellant knew Mr. Turner. There is no
evidence that the respondent was orally appointed an agent by
the appellant or that he was so placed in a situation by the appel-
15 lant, in which, according to the ordinary usage of mankind, it
could be understood that the respondent was an agent of the
appellant.
With regard to the finding of the trial judge that on the evidence
the relationship of agent and principal existed between the res-
20 pondent and the appellant, I cannot find myself in agreement
with him. The trial judge also said in his judgment that "the
relationship between the plaintiff and the defendant as disclosed
in the paper writing was one of principal and agent." The paper
writing referred to is the document dated December 3rd, 1968.
25 [The learned Justice of Appeal read the document again and
continued:] The trial judge said that on the true interpretation
of the document there was the relationship of principal and agent
between the appellant and respondent.
The object of construction of a document is to discover the
30 intention of the parties to the document. There is always the
presumption that the parties have intended what in fact they have
said. The cardinal rule is that the words must be construed as they
stand. See British Movietonews Ltd. v. London & District Cinemas
Ltd. (1 ). It is said in construction that "one must consider the
35 meaning of the words used, not what one may guess to be the
intention of the parties." See Smith v. Lucas (5) (18 Ch.D at
542; 45 L.T. at 462). To ascertain the intention of the parties, the
agreement is to be construed with reference to its object, and the
entire context must be considered to discover the intention of the
40 parties. The object of this document is undoubtedly to erect
buildings on the land the appellant purchased from the respondent.
330
MENDEKIA v. BERESFORD-COLE, 1972-73 ALR S.L. 321
C.A.
I have not been able to find any passage in it which gives the
slightest indication that it creates the relationship of principal and
agent between the appellant and the respondent. In the case of
agency, the relationship creates a situation whereby the agent is
able to affect the principal's legal position in respect of strangers. 5
There is nothing in this document which could be interpreted to
the effect to give the respondent authority either express or
implied to affect the appellant's legal position with a third party.
The evidence itself does not say that the appellant was either a
disclosed or undisclosed principal. In fact, there is no evidence 10
that the appellant met Mr. Turner or that he or any of the work-
men was engaged as alleged by the respondent.
Dr. Marcus-Jones argued that the document was not a contract
but a receipt for money received. The document speaks for itself
and it cannot under any circumstances be regarded as a receipt. 15
The respondent issued a receipt for the subsequent balance of
Le10,000 when that amount was paid by the appellant. The
receipt is a printed receipt and it is in this form:
"Marjay Development Co. 23 Liverpool Street
Freetown Sierra Leone P .0. Box 312. 20
Receipt
Received from Sahr Lebbie Mendekia at 27 Y aradu Road,
Koidu Town the sum of ten thousand leones amount paid in
settlement of the estimated costs of construction of a two-
storey building off Kissy By-Pass Road. Le10,000." 25
It is clear that the respondent has printed receipts which he
issues whenever he receives money from people. Exhibit D is an
example of such receipts. But the document dated December 3rd,
1968 is different, and after reading it carefully, I have no doubt
that it is a building contract entered into by the appellant and 30
respondent. The document refers to the receipt of Le14,000 as
one of the terms of the contract. It also refers to the payment of
the balance of Le10,000 which is another term of the contract.
I therefore hold that the document is a valid building contract.
Having found that it is a valid building contract, the next question 35
to be determined is whether there was a breach of the contract.
One of the terms of the contract was that the buildings were to
be erected on the land "within a maximum period of 6 (six)
calendar months" from December 3rd, 1968. The respondent
failed to complete the buildings within the time stipulated. He 40
asked for a period of another month according to the appellant.
331
THE AFRICAN LAW RE;POR TS
This extra period was permitted the respondent, and again he
failed to complete the building. By letter dated June 11th, 1969,
the respondent wrote to the appellant as follows:
"Mendekia Flats - Kissy
5 I write to say that the costs of construction of the 4 (four)
flats as above is now in the region of Le30,000 (thirty
thousand leones), the total estimated cost of completion is
now as in the attached schedule in the sum of Le36,209.95
(thirty-six thousand two hundred and nine leones, ninety-five
10 cents) which amount exceeds the original costs as estimated,
without drawings, by Le12,209.95 (twelve thousand two
hundred and nine leones, ninety-five cents).
I will be grateful if you will pay this difference of
Le12,209.95 (twelve thousand two hundred and nine leones,
15 ninety-five cents) to me as soon as possible to enable me to
complete construction as scheduled."
I have now to consider whether time was the essence of the
contract between the appellant and the respondent. I have already
found that the contract between the appellant and the respondent
20 was a building contract. The contract was undoubtedly a lump
sum contract. The maximum period within which the buildings in
this case were to be completed was six calendar months. It is
clear from the evidence that the respondent did not complete the
buildings within six calendar months.
25 The law is that where a particular time for completion is speci-
fied in the contract, the mere fact of non-completion within that
time will not in ordinary circumstances be such a breach as to
release the employer from the contract, but it may entitle him to
damages. But when the contract expressly makes time of the
30 essence of the contract, then time will be a material factor of the
contract. Generally in building contracts time is not of the essence
of the contract in the absence of express words making it so.
In the present case, it was agreed between the parties that the
completion of the four flats would take six calendar months.
35 There was evidence that the appellant wanted to let out the flats.
And since the respondent failed to perform his part of the contract
within the stipulated time, I hold that he has committed a breach
of contract. But the respondent further said that he was unable
to complete the building of the four flats owing to the rise in
40 costs of materials and labour. It seems to me that what the respon
dent was saying was that the contract had been repudiated because
of the rise in costs of materials and labour.
332
MENDEKIA v. BERESFORD-COLE. 1972-7 3 ALR S.L. 321
C.A.
Where a change of circumstance after the formation of a
contract makes it impossible to fulfil the contract, then the
doctrine of frustration becomes relevant. With regard to building
contracts, it is said that "it is not hardship or inconvenience or
material loss itself which calls the principle of frustration into 5
play." See Davis Contractors Ltd. v. Fareham U.D.C. (2) ([1956]
A.C. at 729; [1956] 2 All E.R. at 160). In this case, the plaintiffs
agreed to build 78 houses for the defendants at a fixed price, the
work to be completed in eight months. Due partly to bad weather,
but also to an unforeseen shortage of labour caused by the un· 10
expected lag in the demobilisation of troops after the war, the
work took 22 months to complete, and cost the builers some
£17,000 more than they anticipated. The builders claimed that
the shortage of labour and the delay had frustrated the contract.
The House of Lords unanimously held that the contract had not 15
been frustrated. In the same case Viscount Simonds ([1956 A.C.
at 716; [1956] 2 All E.R. at 151) denied that-
"where, without the default of either party, there has been
an unexpected turn of events, which renders the contract
more onerous than the parties had contemplated, that is by 20
itself a ground for relieving a party of the obligation he has
undertaken."
Lord Reid said ([1956] A.C. at 724; [1956] 2 All E.R. 156):
" ... · [T] he delay was greater in degree than was to be expec.
ted. It was not caused by any new and unforeseeable factor 25
or event: the job proved to be more onerous but it never
became a job of a different kind from that contemplated in
the contract."
A builder who undertook to perform such work for a definite
lump sum undertook the commercial risk that delay would increase 30
his cost.
In the case of Parkinson (Sir Lindsay) & Co. Ltd. v. Com mrs.
of Works (4) Asquith, L.J. laid down the following principles
([1949] 2 K.B. at 665; [1950] 1 All E.R. at 228):
"A contract often provides that in the event of 'delay' 35
through specified causes, the contract is not to be dissolved,
but merely suspended, yet such a provision has been held not
to apply where the delay was so abnormal, so pre.emptive,
as to fall outside what the parties could possibly have con·
templated in the suspension clause. In other words 'delay' 40
though literally describing what has occurred, has been read
as limited to normal, moderate delay, and as not extending
333
THE AFRICAN LAW REPORTS
to an interruption so differing in degree and magnitude
from anything which could have been contemplated as to
differ from it in kind."
The facts in the present case are almost identical with the facts
5 in Davis's case (2). The contract was a lump sum contract and the
respondent undertook the risk that might have occurred owing to
the rise in costs of materials and labour. Moreover, the respondent
did make provision for such risks in the agreement when he
estimated the sum of Le800 for exigencies. It is therefore my view
10 that the contract was not frustrated and that the conduct of the
respondent amounted to a breach of contract.
I shall now deal with measure of damages in respect of breach
of contract by a contractor. This subject was dealt with in the
case of Mertens v. Home Freeholds Co. (3) and the proposition in
15 the case was that the measure of damages for failure by the con
tractor to complete a building or engineering contract will include
first, the difference (if any) between the price of the work as
agreed upon the contract and the cost the employer is actually
put to in its completion, and cost of completion means cost of
20 the completion of the contract work itself. There is evidence that
the agreed contract price between the appellant and the respon
dent was the sum of Le24,000. John Thompson, a chartered
quantity surveyor gave evidence on behalf of the plaintiff. In
January 1971, this witness estimated the value of the work
25 required to complete the block of flats off Kissy By-Pass Road. In
his opinion the total sum of Le1 7,450 was the amount required
to complete the block of flats. He estimated the costs of internal
works and drainage at the sum of Le3,370. But looking at the
agreement there was no provision for external works and drainage
30 the cost of which was included in the sum of Le17 ,450. Basing
my calculation on Mertens' case, I would award the appellant
the sum of Le14,085 as damages for breach of contract, and I
so award.
The appellant also claimed the sum Le4 ,800 for loss of rent.
35 The appellant gave evidence that he made it known to the respon
dent that he intended to let out the flats. He did not say for what
amount he intended to let the flats. Even if he had given evidence
that he intended to let each flat at specific rate, this piece of
evidence would be too vague, as no one could be certain of what
40 amount a tenant would be prepared to pay. However, there is
no evidence that the appellant had had an offer from a prospective
334
MENDEKIA v. BERESFORD-COLE,1972-73 ALR S.L. 321
C.A
tenant to pay any specific sum monthly as rent. In the circum
stance, I hold that the appellant failed to prove that as a result
of the respondent's breach of contract, he suffered loss to the
extent of the sum of Le4,800 or any loss at all.
With regard to the claim of Le500 as professional fees, there 5
is evidence that Mr. Thompson was paid the sum of Le500 and
a receipt for this amount was put in evidence. I am satisfied that
this amount was paid by the appellant to Mr. Thompson.
Taking all the circumstances into consideration, I allow the
appeal and make the following orders: 10
(1) That the respondent pay to the appellant the sum of
Le14,085 as general damages;
(2) that the respondent pay to the appellant the sum of
Le500 as special damages, and
( 3) that the costs of the claim in the High Court, the costs of 15
the appeal in this court and the costs of the respondent's
notice be paid by the respondent.
Order accordingly.
20
25
30
35
40
335
