November 2, 1960
IN THE COURT OF APPEAL
Freetown Cold Storage Co. Ltd & Anor
Appellant
v.
Flower Garden Contractors
Respondent
CIV APP 27 of 1960
[1960] SLCA 1
Proceeding. Civil appeal. Sierra Leone.
Held. (1) that respondent's damages for breach of the contract should be
arrived at by taking the last two instalments of the contract price (£267 12s. Od.)
and subtracting therefrom the cost of hiring 12 labourers at 6s. 4d. each per
day for 52 days (£197 12s. Od.), leaving a total of £70 Os. Od.;
(2) that, though respondent's claim for £37 9s. 6d. for missing tools was a
claim in tort, the trial judge acted properly in entertaining it in order to avoid
multiplicity of actions; and
(3) that the trial judge was correct in awarding respondent £50 10s. Od. for
the supply of 101 bags of grass.
is common form throughout West Africa for the employment by mercantile
companies of their storekeepers, clerks and produce buyers. Such agreements
have often been put in evidence before the courts. I cannot recollect any case,
in my many years upon the Bench, in which a court has held, or in which it
was suggested that a court should hold, that such an agreement constituted a
yearly hiring. On the contrary they have been held to be terminable on the
giving of the notice specified therein.
[COURT OF APPEAL)
FREETOWN COLD STORAGE CO. LTD
v.
BRIGHT'S CONSTRUCTION AND FLOWER GARDEN
CONTRACTORS
[Civil Appeal 27/60]
Appellant.J
Respondent
Contract-Breach of contract-measure of damages-Multiplicity of actions.
Appellants and respondent entered into a written contract whereby respon
dent agreed to do certain work for appellants for the sum of £535 4s. Od. to
be paid in four equal instalments of £133 16s. Od. each. After respondent had
commenced work and received two instalments totalling £267 12s. Od. appellants
discharged him in breach of the contract. Respondent brought suit in the
Supreme Court, which gave judgment for them in the amount of £405 lls. 6d.
Appellants appealed on the ground, inter alia, that the damages were excessive.
Held, (1) that respondent's damages for breach of the contract should be
arrived at by taking the last two instalments of the contract price (£267 12s. Od.)
and subtracting therefrom the cost of hiring 12 labourers at 6s. 4d. each per
day for 52 days (£197 12s. Od.), leaving a total of £70 Os. Od.;
(2) that, though respondent's claim for £37 9s. 6d. for missing tools was a
claim in tort, the trial judge acted properly in entertaining it in order to avoid
multiplicity of actions; and
(3) that the trial judge was correct in awarding respondent £50 10s. Od. for
the supply of 101 bags of grass.
Edward J. McCormack for the appellants.
Respondent in person.
BENKA-CoKER Ao. C.J. In an action instituted in the Supreme Court of
Sierra Leone by the above-named respondent, Bright Construction and Flower
Garden Contractors (in fact Rowland Mansfield Bright), against the appellants
claiming damages for breach of contract the Supreme Court gave judgment
for the respondent and awarded the respondent £50 general damages and
£355 lls. 6d. special damages, making in all £405 lls. 6d.
The appellants appealed against the said judgment on the following
grounds: (i) that the decision is against the weight of evidence ; (ii) that the
damages are excessive.
On the hearing of the appeal counsel for the appellants by leave of the
court added and argued the following ground: Particulars of misdirection.
The learned trial judge did not award damages on the basis of a quantum
meruit as he should have done.
On August 14, 1958, the appellants and the respondent entered into a written
agreement whereby the appellants agreed to employ the respondent to carry
139
C. A.
1960
UNITED
AFRICA
COMPANY
V.
KALLAY.
Wiseham C.J.
Freetown
Nov. 2,
1960
Ames P
Benka-Coker
Ag. C.J.
Wiseham C.J.
c. A.
1960
F'REETOWN
CoLD
STORAGE
Co. LTD.
v.
BRIGHT'S.
Benka-Coker
Ag.C.I.
out cleaning, ploughing and planting at the appellants' compound at Knox
Farm, King Tom, and to pay the respondent the sum of £535 4s. Od. (in four
equal instalments of £133 16s. Od.) and the cost of any grass supplied by the
respondent. The work was to be carried out by the respondent within four
months of 26 days.
The sum of £535 4s. Od. was the sum total of the detailed estimate sub
mitted by the respondent for the carrying out of the work and the details of the
estimate are as follows:
12 labourers @ 6/4 per day for four months of 26 days
Transportation of clearance @ 45 I- per trip for 20 days
Ploughing machine on hire @ £5 per acre for three acres
Supervision for four months @ £20 per month ...
£395 4s. Od.
£45 Os. Oct.
£15 Os. Od.
£80 Os. Od.
£535 4s. Od.
On October 14, 1958, i.e., two months before the contract was to be fully
performed, the appellants' solicitor wrote to the respondent terminating the
agreement before the respondent had completed the execution of the work.
Appellants' counsel having in this court admitted that there was a breach
of the contract by the appellants as found by the trial judge, it is only for
us now to decide whether the damages awarded are excessive.
It is not disputed that the respondent has received the sum of £267 12s. Od.
under the contract and that if the respondent had been allowed to complete
the execution of the work, he would have been entitled to receive a further
sum of £267 12s. Od. and nothing more. The appellants' contention is that the
respondent should not have been awarded general damages of £50 and that the
amount for special damages should have been reduced by the amount he would
have expended in executing the rest of the contract. The appellants' claim in
this action is for damages for breach of contract.
The loss to the plaintiffs in this case is the opportunity to earn the last
two instalments of £133 16s. Od. each-£267 12s. Od. less the cost of hiring of
12 labourers @ 6s. 4d. each per day for two months of 26 days each=
£197 12s. Od., i.e., £70 Os. Od. As regards the claim for missing tools, the only
submission made by the appellants' solicitor before us is that this is a claim
in tort and does not arise out of the breach of the contract. We agree that
this is not properly a loss arising out of the breach of the contract by the
appellants, but as we are of opinion that an action could properly have been
instituted in tort for conversion, and as we see no reason for interfering with
the trial judge's finding in this regard, we think that the trial judge acted
properly in entertaining this claim in order to avoid multiplicity of actions.
We confirm the award of £37 9s. 6d. The appellants have not disputed
in this court liability to pay the sum of £50 10s. Od. claimed by the respondent
for the supply of 101 bags of grass, and we confirm the award of £50 10s. Od.
in that regard.
The net result would therefore be as follows: (a) damages £70 Os. Od.;
(b) missing tools £37 9s. 6d.; (c) 101 bags of grass £50 10s. Od. Total
£157 19s. 6d.
We order that judgment should be entered in the court below fot the
respondent in the sum of £157 19s. 6d. instead of £405 11s. 6d. The appellants
to have the costs of this appeal to be taxed.
140